Pakistan’s four telecom operators have jointly asked the government to charge them industrial electricity rates instead of commercial rates for their network sites, and the Prime Minister’s Office directed a task force on 11 November 2026 to finalise recommendations. No decision has been announced yet. The operators say cheaper power will protect about $2 billion of planned investment in 5G, fibre and data centres over the next three years.
Who asked for cheaper electricity, and what exactly do they want?
The chief executives of Jazz, CMPak (Zong), PTML (Ufone and Telenor) and PTCL wrote jointly to Prime Minister Shehbaz Sharif. They want industrial electricity tariffs extended to licensed telecom infrastructure, or a new Digital/Telecom Infrastructure consumer category charged at industrial rates. Their argument is that telecom has been recognised as an industry under government policy and legislation, yet operators still pay the much higher commercial tariff for the power their towers consume.
The cheaper rate would not apply to everything an operator owns. It would cover only PTA-certified infrastructure: cellular towers and base transceiver stations, switching centres, exchanges, data centres, fibre-to-the-home nodes and network operations centres. Offices, franchises and retail outlets would keep paying commercial rates.
Why are the operators asking now?
The operators say their power bills have become a threat to the 5G rollout. According to their own submissions, commercial electricity tariffs for telecom sites have risen by about 197% since 2018, while fuel costs for running sites have risen by around 300% in the same period. Average revenue per user has fallen by about 22% over the same years. These are the industry’s own figures and have not been independently verified, but they explain the timing: 5G sites use more power than 4G sites, and the rollout is still in its early phase.
Ufone Weekly Power Grand and Mega Offer 2026Pakistan’s nationwide 5G rollout is expected to take about another two years. Jazz, Zong and Ufone hold 5G licences and have switched 5G on in 24 cities so far, with about 1,782 live sites and 1.8 million users as of October 2026. The operators warn that if power costs keep rising, the pace of that rollout will slow.
What has the government decided so far?
Nothing final. A task force headed by the Secretary of the Ministry of Information Technology and Telecommunication was formed on 29 June 2026 to examine industrial power tariffs for telecom, along with smart-grid solutions and dedicated power feeders. Its first meeting was held on 4 August 2026, and on 11 November 2026 the Prime Minister’s Office directed it to finalise recommendations.
The task force must now consult the Power Division and the Finance Division and submit proposals covering the financial implications and a mechanism to absorb the difference between commercial and industrial rates. The federal government will then decide. The tariff has not changed, and no rupee figure for a new rate has been announced.
What is the $2 billion pledge?
The operators have committed about $2 billion over the next three years for 5G deployment, fibre expansion and AI-ready Tier-III data centres. They have pledged to reinvest any savings from cheaper electricity into 5G expansion, rural coverage and fibre-to-the-home services. They also argue that higher electricity consumption from a bigger network could offset the distribution companies’ lost revenue within two to three years — again, an industry estimate, not an independent finding.
Will cheaper power mean cheaper mobile packages?
Not automatically, and readers should not expect it. A lower electricity bill cuts the operators’ operating costs, but package prices depend on many other things: spectrum fees, taxes, competition, and the cost of the rollout itself. The operators’ pledge is to reinvest savings into the network, not to cut prices. If the tariff changes, the honest benefit for users is a faster 5G rollout and better coverage — not a cheaper bundle the next morning.
What happens next?
The task force submits its recommendations to the federal government after consulting the Power Division and the Finance Division. If the government approves, it would issue a formal policy directive extending industrial rates to eligible infrastructure or creating the new consumer category. Until then, operators keep paying commercial rates, and the 5G rollout continues on the current cost base. This page will be updated when the task force reports or the government decides.
Frequently asked questions
Why do telecom operators want industrial electricity tariff?
They say commercial power tariffs for their sites have risen about 197% since 2018, while fuel costs rose about 300%, and that cheaper power is needed to protect the 5G rollout.
Has the government approved cheaper electricity for telcos?
No. On 11 November 2026 the Prime Minister’s Office directed a task force to finalise recommendations. No final decision has been announced.
Which companies made the request?
The chief executives of Jazz, CMPak (Zong), PTML (Ufone and Telenor) and PTCL, in a joint request to Prime Minister Shehbaz Sharif.
How much have operators pledged to invest in 5G?
About $2 billion over three years for 5G deployment, fibre expansion and AI-ready Tier-III data centres.
Will my mobile package get cheaper if the tariff changes?
Not necessarily. The operators pledged to reinvest savings in the network. The likely benefit is a faster 5G rollout, not an immediate price cut.